Island 191 plot k – Zopah – ABOMEY-CALAVI

COMPLETION OF EXECUTION STUDIES AS PART OF THE CONSTRUCTION WORK FOR STORM COLLECTORS AND RELATED ROAD DEVELOPMENT IN THE PA3 BASINS AND IN THE CITY OF COTONOU (LOT PAPC-BM_T01)

YearDecember 2021 – in progress
CustomerHunan Road and Bridge Construction (HNRB)
Project Owner / Delegated Project OwnerMinistry of the Living Environment and Sustainable Development (MCVDD) & AGETUR SA
CountryBenin

Role in the mission

Subcontracting contract for the technical studies of execution

  • Geometric design (plan view, long profile, cross profiles of streets and collectors and retention basins)
  • Development of the standard plans
  • Sizing of the various works accompanied by calculation notes and formwork and reinforcement plans
  • Sizing of the pavement structure
  • Dimensioning of the public lighting system with installation plans of the blocks and the sizing note for the blocks and anchor rod as well as the results of photometric calculations
  • Design of landscaping
  • Implementation of road signage plans
  • Carrying out the execution studies of the AEP network