COMPLETION OF ADDITIONAL EXECUTION STUDIES AND THE EXECUTION STUDY OF A 40X20 SECTION PLATFORM ON THE CHANNEL AS PART OF THE BEACH DEVELOPMENT PROJECT BETWEEN MARIE-STELLA AND ADOUNKO (12.5 KM)
YearJanuary 2024 – in progress
CustomerHITECH-ITB BENIN
Project Owner / Delegated Project OwnerSIRAT SA
CountryBenin
Role in the mission
Subcontracting contract for the technical studies of execution
The project concerns
- Sizing of the platform 20x40m
- The development of a walk between Marie-Stella and Adounko
- Resumption of the execution studies for zones 1, 2, 3 and 4
- Resumption of the execution studies for zones 1, 2, and 4
- Geometric design (plan view, long profile, cross profiles of the layouts)
- Development of the standard plans
- Sizing of the various works accompanied by calculation notes and formwork and reinforcement plans
- Sizing of the pavement structure
- Elaboration des plans d’implantation de la plateforme
- Implementation of road signage plans
- Carrying out the execution studies of the AEP network