COMPLETION OF EXECUTION STUDIES AS PART OF THE CONSTRUCTION WORK FOR STORM COLLECTORS AND RELATED ROAD DEVELOPMENT IN THE PA3 BASINS AND IN THE CITY OF COTONOU (LOT PAPC-BM_T01)
YearDecember 2021 – in progress
CustomerHunan Road and Bridge Construction (HNRB)
Project Owner / Delegated Project OwnerMinistry of the Living Environment and Sustainable Development (MCVDD) & AGETUR SA
CountryBenin
Role in the mission
Subcontracting contract for the technical studies of execution
- Geometric design (plan view, long profile, cross profiles of streets and collectors and retention basins)
- Development of the standard plans
- Sizing of the various works accompanied by calculation notes and formwork and reinforcement plans
- Sizing of the pavement structure
- Dimensioning of the public lighting system with installation plans of the blocks and the sizing note for the blocks and anchor rod as well as the results of photometric calculations
- Design of landscaping
- Implementation of road signage plans
- Carrying out the execution studies of the AEP network