MISSION D’ETUDES DE FAISABILITE DES TRAVAUX D’AMENAGEMENT DES PISTES RN23-CS-Gandjagbédji, Akplégbonou–Maïboui–Kantiannou (Doutou), Adounhonto–Aclo (Dahè), RN23–Carrefour Adjamè, Kpakossouhoué–faces de l’EUC de Sè, Loufagnigbonou–Adromè–Zindhihoué, Doutou–Gavè–Honhoué, Zoungbonou–Tohonou, CSA Adromè–Dodji–Didongbigo, Honhoué–Djibio–Dahè, Adromè–Gbèto–Gbagbonou, RN23–Honhoué
YearFévrier 2025-Juin 2025
CustomerMAIRIE DE HOUEYOGBE
Project Owner / Delegated Project OwnerMAIRIE DE HOUEYOGBE
CountryBenin
Role in the mission
Contrat pour les études techniques des travaux d’aménagement de 50 km de pistes rurales
The project concerns
- Geometric design (plan view, long profile, cross profiles of the layouts)
- Etudes des points critiques
- Development of the standard plans
- Sizing of the various works accompanied by calculation notes and formwork and reinforcement plans
- Sizing of the pavement structure
- Carrying out hydrological and hydraulic studies
- Implementation of road signage plans