PROJECT MANAGEMENT OF THE CONSTRUCTION WORK ON TWO EXPLOITATION BOREHOLES EQUIPPED WITH PVC AS PART OF THE ROAD CLEARANCE WORKS MISSESSINTO - ALLADA
YearMay 2023 – in progress
CustomerPORTEO BENIN SA
Project Owner / Delegated Project OwnerSIRAT SA
CountryBenin
Role in the mission
Technical execution studies, the supervision of the construction work for two boreholes on the life base of the company PORTEO BENIN
The project concerns
- The completion of two drillings to a depth of 80m
- The PVC drilling equipment 126 140
- The realization of the drilling head
- The cleaning of drilling
- The conduct of short-term pumping tests
- The installation of the submerged pump and its wiring