COMPLETION OF EXECUTION STUDIES AS PART OF THE REHABILITATION AND DEVELOPMENT WORKS OF ROADS IN THE VIILLES OF BENIN – ASPHALTING PHASE B3 (LOT 3B BIS – FIDJROSSE AND TOGBIN AREA)
YearApril 2024 – in progress
CustomerHNRB
Project Owner / Delegated Project OwnerSIRAT SA
CountryBenin
Role in the mission
Subcontracting contract for the technical studies of execution
The project concerns
- Sizing of 36 km of asphalt or paved roads
- Sizing of 60 km of lateral gutters
- The layout of 3 km of collectors
- Sanitation by reshaping the schoolyard
- Geometric design (plan view, long profile, cross profiles of the layouts)
- Development of the standard plans
- Sizing of the various works accompanied by calculation notes and formwork and reinforcement plans
- Sizing of the pavement structure
- Carrying out hydrological and hydraulic studies